Vinata Tower includes 24-storey and 2 basements with 23.387 m2, the apartment building is the pilot to use comprehensive BIM. This is the first project Vinata apply BIM to realize the benefit of BIM and create a standard process for the coming projects.
Project information
Project type: Apartment
Location: Vietnam
Scale: 23 387m2
Owner: Vinata international co.,ltd
Consultancy: ViBIM
Scope of work:Modeling from 2D CAD to 3D on LOD 300, system coordination, clash avoidance, shop drawings production and model based-quantity takeoff The project devices into 3 packages:
Package 1: Coordinate and design control (for both of design and field management, including: Planning BIM application strategy, execution planning, sample project setting; set up platform for data exchange; remodel all of building disciplines; check clashes trade building; identify design error and signification conflict; coordination meeting with employer and contractor; modeling meticulous the important areas)
Package 2: Pre-construction phase
Detail model 1 mock-up room (for design)
Model temporary system: scaffolding, mast crane, hoist…, quantity take off and purge employer’s schedule; integrate model of temporary system, structure model, site model, construction schedule in plan/ reality to model construction sequence from basement; update adjustment construction schedule (for construction activities)
Package 3: As-built modeling and quantity takeoff (don’t include as-built draw)
According to requirement of employer and particularity of project, ViBIM assists to Vinata use five BIM applications by the latest version appropriate software , including:
BIM APPLICATION | DISCIPLINES | SOFTWARE USING | VERSION |
Design Authoring (Convert 2D AutoCAD Drawing to 3D Revit/Tekla model) | Architecture MEP Structure | Revit, Tekla | 2016
|
Design Reviews (Identify clashes and mistake from 2D design documentation in the progress of modeling) | Architecture MEP Structure | Revit, Naviswork | 2016 |
3D Coordination (Clashes detection all of building disciplines) | Architecture MEP Structure | Naviswork Manage 2016 | 2016 |
Site Utilization Planning
(Sequence and construction method simulation by integrating BIM model and schedule) | Architecture MEP Structure | Naviswork Manage 2016 | 2016
|
Cost Estimation (Quantity takeoff all of building elements in BIM environment)
| Architecture MEP Structure | Revit, Naviswork | 2016 |
Purpose to apply BIM for project:
Level of priority | Purpose | Potential BIM application |
1 | Consider benefit of applying BIM to project | BIM Execution Plan |
2 | Reduce design error affect to construction activities at the site | Design Review and 3D Coordination |
1 | As-built modeling with fulfill data for O&M activities | Record Model, 3D Coordination |
1 | Tracking and Reviewing construction schedule and sequence at the site | 4D modeling-construction sequencing |
2 | Review integrated design documentation | 3D design Reviews |
3 | Review and compare BIM quantity takeoff to tradition | 3D Clashes detection |
After each time of change, the control old and new error and update clashes report are automatic according to process.