Case study for BIM application into Vinata Tower

Vinata Tower includes 24-storey and 2 basements with 23.387 m2, the apartment building is the pilot to use comprehensive BIM. This is the first project Vinata apply BIM to realize the benefit of BIM and create a standard process for the coming projects.

Project information
Project type: Apartment
Location: Vietnam
Scale: 23 387m2
Owner: Vinata international co.,ltd
Consultancy: ViBIM
Scope of work:Modeling from 2D CAD to 3D on LOD 300, system coordination, clash avoidance, shop drawings production and model based-quantity takeoff
The project devices into 3 packages:
Package 1: Coordinate and design control (for both of design and field management, including: Planning BIM application strategy, execution planning, sample project setting; set up platform for data exchange; remodel all of building disciplines; check clashes trade building; identify design error and signification conflict; coordination meeting with employer and contractor; modeling meticulous the important areas)
architecture model
structure model

MEP model
Tekla model
Package 2: Pre-construction phase
Detail model 1 mock-up room (for design)
Model temporary system: scaffolding, mast crane, hoist…, quantity take off and purge employer’s schedule; integrate model of temporary system, structure model, site model, construction schedule in plan/ reality to model construction sequence from basement; update adjustment construction schedule (for construction activities)

Basement model

typical room model
Package 3: As-built modeling and quantity takeoff (don’t include as-built draw)
According to requirement of employer and particularity of project, ViBIM assists to Vinata use five BIM applications by the latest version appropriate software , including:

BIM APPLICATION

DISCIPLINES

SOFTWARE USING

VERSION

Design Authoring

(Convert 2D AutoCAD Drawing to 3D Revit/Tekla model)

Architecture

MEP

Structure

Revit, Tekla

2016

Design Reviews

(Identify clashes and mistake from 2D design documentation in the progress of modeling)

Architecture

MEP

Structure

Revit, Naviswork

2016

3D Coordination

(Clashes detection all of building disciplines)

Architecture

MEP

Structure

Naviswork Manage 2016

2016

Site Utilization Planning

(Sequence and construction method simulation by integrating BIM model and schedule)

Architecture

MEP

Structure

Naviswork Manage 2016

2016

Cost Estimation

(Quantity takeoff all of building elements in BIM environment)

Architecture

MEP

Structure

Revit, Naviswork

2016


Purpose to apply BIM for project:

Level of priority

Purpose

Potential BIM application

1

Consider benefit of applying BIM to project

BIM Execution Plan

2

Reduce design error affect to construction activities at the site

Design Review and 3D Coordination

1

As-built modeling with fulfill data for O&M activities

Record Model, 3D Coordination

1

Tracking and Reviewing construction schedule and sequence at the site

4D modeling-construction sequencing

2

Review integrated design documentation

3D design Reviews

3

Review and compare BIM quantity takeoff to tradition

3D Clashes detection

After each time of change, the control old and new error and update clashes report are automatic according to process.
Tác giả: Quynh Pham